Public Works
Project Status Update
US 41 Storm Structures
John DeGiovine, Project Manager
This project involves engineering and permitting for the directional drilling of culverts under US 41 at the Fordham, Elkcam, and Pompano Waterways; replacement of culverts at the North and South US 41 Access Roads, within the Pompano Waterway; replacement of a stand-alone weir across the Elkcam Waterway, north of the US 41 Access Road; and replacement of a stand-alone weir across the Fordham Waterway, north of the US 41 Access Road.
Future dates and durations associated with this project are approximations and are dependent on funding, permitting, weather, and contractor availability. Permitting for some projects, depending on their complexity, can take years to obtain.
Project Task |
Start Date |
Finish Date |
% Complete |
Contractor |
|---|---|---|---|---|
| Design | 04/10/08 |
08/31/10 |
57% |
|
Data Collection |
04/10/08 |
06/10/08 |
100% |
|
Stormwater Model Runs |
04/10/08 |
07/31/09 | 100% | |
30% Plans |
02/01/09 |
03/31/10 |
20% |
|
60% Plans |
04/02/10 |
06/30/10 |
0% |
|
90% Plans |
07/30/10 |
08/30/10 |
0% |
|
Final Plans |
08/31/10 |
08/31/10 |
0% |
|
| Permitting | 10/24/08 |
08/30/10 |
47% |
|
FDOT |
10/24/08 |
12/30/09 |
60% |
|
SWFWMD (Conceptual) |
10/29/08 |
06/30/10 | 75% | |
SWFWMD (Construction) |
04/02/09 |
05/31/10 |
0% |
|
Bid and Construction Services |
06/28/10 |
08/30/10 |
0% |
|
| Construction* | 06/28/10 |
08/26/11 |
0% |
|
Documents to Purchasing |
06/28/10 |
06/28/10 |
0% |
|
Checklist Process |
06/28/10 |
06/28/10 |
0% |
|
Pre-Bid Date Scheduled |
07/28/10 |
07/28/10 |
0% |
|
Bid Opening |
08/11/10 |
08/11/10 |
0% |
|
Goldenrod Preparation |
08/12/10 |
08/12/10 |
0% |
|
BCC Approval |
08/13/10 |
08/13/10 |
0% |
|
Pre-Construction Meeting |
08/18/10 |
08/18/10 |
0% |
|
Notice to Proceed |
08/19/10 |
08/19/10 |
0% |
|
Construction |
08/20/10 |
08/20/11 |
0% |
|
Substantial Completion/Rating |
08/21/11 |
08/21/11 |
0% |
|
Punchlist Items |
08/22/11 |
08/22/11 |
0% |
|
As-Builts Received |
08/23/11 |
08/23/11 |
0% |
|
Submit As-Builts |
08/24/11 |
08/24/11 |
0% |
|
Final Invoice from Contractor |
08/25/11 |
08/25/11 |
0% |
|
Close Project |
08/26/11 |
08/26/11 |
0% |
* Phase 2 of the Midway CIP improvements.