US 41 Storm Structures

John DeGiovine, Project Manager

This project involves engineering and permitting for the directional drilling of culverts under US 41 at the Fordham, Elkcam, and Pompano Waterways; replacement of culverts at the North and South US 41 Access Roads, within the Pompano Waterway; replacement of a stand-alone weir across the Elkcam Waterway, north of the US 41 Access Road; and replacement of a stand-alone weir across the Fordham Waterway, north of the US 41 Access Road.

Future dates and durations associated with this project are approximations and are dependent on funding, permitting, weather, and contractor availability. Permitting for some projects, depending on their complexity, can take years to obtain.

Project Task
Start Date
Finish Date
% Complete
Contractor
Design
04/10/08
08/31/10
57%
 
Data Collection
04/10/08
06/10/08
100%
 
Stormwater Model Runs
04/10/08
07/31/09 100%  
30% Plans
02/01/09
03/31/10
20%
 
60% Plans
04/02/10
06/30/10
0%
 
90% Plans
07/30/10
08/30/10
0%
 
Final Plans
08/31/10
08/31/10
0%
 
Permitting
10/24/08
08/30/10
47%
 
FDOT
10/24/08
12/30/09
60%
 
SWFWMD (Conceptual)
10/29/08
06/30/10 75%  
SWFWMD (Construction)
04/02/09
05/31/10
0%
 
Bid and Construction Services
06/28/10
08/30/10
0%
 
Construction*
06/28/10
08/26/11
0%
 
Documents to Purchasing
06/28/10
06/28/10
0%
 
Checklist Process
06/28/10
06/28/10
0%
 
Pre-Bid Date Scheduled
07/28/10
07/28/10
0%
 
Bid Opening
08/11/10
08/11/10
0%
 
Goldenrod Preparation
08/12/10
08/12/10
0%
 
BCC Approval
08/13/10
08/13/10
0%
 
Pre-Construction Meeting
08/18/10
08/18/10
0%
 
Notice to Proceed
08/19/10
08/19/10
0%
 
Construction
08/20/10
08/20/11
0%
 
Substantial Completion/Rating
08/21/11
08/21/11
0%
 
Punchlist Items
08/22/11
08/22/11
0%
 
As-Builts Received
08/23/11
08/23/11
0%
 
Submit As-Builts
08/24/11
08/24/11
0%
 
Final Invoice from Contractor
08/25/11
08/25/11
0%
 
Close Project
08/26/11
08/26/11
0%
 

* Phase 2 of the Midway CIP improvements.