Public Works

Project Status Update

US 41 Storm Structures

John DeGiovine, Project Manager

This project involves engineering and permitting for the directional drilling of culverts under US 41 at the Fordham, Elkcam, and Pompano Waterways; replacement of culverts at the North and South US 41 Access Roads, within the Pompano Waterway; replacement of a stand-alone weir across the Elkcam Waterway, north of the US 41 Access Road; and replacement of a stand-alone weir across the Fordham Waterway, north of the US 41 Access Road.

Future dates and durations associated with this project are approximations and are dependent on funding, permitting, weather, and contractor availability. Permitting for some projects, depending on their complexity, can take years to obtain.

Project Task
Start Date
Finish Date
% Complete
Contractor
Design
04/10/08
08/31/10
57%
 
Data Collection
04/10/08
06/10/08
100%
 
Stormwater Model Runs
04/10/08
07/31/09 100%  
30% Plans
02/01/09
03/31/10
20%
 
60% Plans
04/02/10
06/30/10
0%
 
90% Plans
07/30/10
08/30/10
0%
 
Final Plans
08/31/10
08/31/10
0%
 
Permitting
10/24/08
01/28/11
38%
 
FDOT
10/24/08
12/30/09
60%
 
SWFWMD (Conceptual)
10/29/08
06/30/10 75%  
SWFWMD (Construction)
04/02/09
05/31/10
0%
 
Bid and Construction Services
12/02/09
01/28/11
0%
 
Construction*
11/02/09
01/28/11
0%
 
Documents to Purchasing
11/02/09
11/02/09
0%
 
Checklist Process
11/03/09
11/03/09
0%
 
Pre-Bid Date Scheduled
12/02/09
12/02/09
0%
 
Bid Opening
12/30/09
12/30/09
0%
 
Goldenrod Preparation
12/31/09
12/31/09
0%
 
BCC Approval
01/05/10
01/05/10
0%
 
Pre-Construction Meeting
01/20/10
01/20/10
0%
 
Notice to Proceed
01/21/10
01/21/10
0%
 
Construction
01/22/10
01/22/11
0%
 
Substantial Completion/Rating
01/23/11
01/23/11
0%
 
Punchlist Items
01/24/11
01/24/11
0%
 
As-Builts Received
01/25/11
01/25/11
0%
 
Submit As-Builts
01/26/11
01/26/11
0%
 
Final Invoice from Contractor
01/27/11
01/27/11
0%
 
Close Project
01/28/11
01/28/11
0%
 

* Phase 2 of the Midway CIP improvements.