Project Status Update

Piper Road Widening South
(Henry Street to North Jones Loop)

CIP Project C410202

Brian Barnes, Project Engineer

This project will provide a four-lane, divided arterial (Piper Road, from Henry Street to North Jones Loop), connecting US 17 with Jones Loop Road at I-75. Staff is working with the Airport Authority to combine the stormwater management for both Piper Road and their property into a single system. Negotiations are also underway with other property owners along the roadway for right-of-way, access points, and stormwater facilities.

Future dates and durations associated with this project are approximations and are dependent on funding, permitting, weather, and contractor availability. Permitting for some projects, depending on their complexity, can take years to obtain.

Project Task
Start Date
Finish Date
% Complete
Contractor
Design
01/03/05
07/05/08
100%
Johnson Engineering
30% Review
01/03/05
12/23/05
100%
 
60% Review
12/09/05
11/24/06
100%
 
90% Review
10/08/07
01/07/08
100%
 
100% Review
01/08/08
07/05/08
100%
 
Permitting
11/20/06
09/01/09
100%
 
SWFWMD
11/20/06
03/07/08
100%
 
SWFWMD Airport Permit
09/03/07
04/01/08
100%
 
Right-of-Way
10/01/08
09/01/09
100%
 
Construction 01/04/10 07/04/11
0%
 

Comments:

The project will be built in phases, in cooperation with developers.

Comments:

The project will be built in phases, in cooperation with developers.