Project Task
Start Date
Finish Date
% Complete
Contractor
Construction 09/01/09 05/15/11 2%  
Documents to Purchasing
09/01/09 09/01/09
100%
 
Pre-Bid Meeting
09/15/09 09/15/09 100%  
Bid Opening
10/07/09 10/12/09 100%  
Goldenrod Preparation 10/12/09 10/16/09 100%  
BCC Approval
10/27/09 10/27/09 0%  
Pre-Construction Meeting
11/04/09 11/04/09 0%  
Respond to RFI's 11/05/09 11/11/09 0%  
Construction 11/05/09 02/12/11 0%  
Substantial Completion 02/13/11 02/13/11 0%  
As-Built Survey 02/14/11 03/15/11 0%  
Punchlist Items 02/14/11 02/27/11 0%  
Project Certification (Submit As-Builts) 03/16/11 05/14/11 0%  
Close Project 05/15/11 05/15/11 0%