Project Task
Start Date
Finish Date
% Complete
Contractor
Request for Proposal
01/07/08
02/14/08
100%
 
Request to Purchasing
01/07/08
01/14/08
100%
 
Proposal Received
01/18/08
01/31/08
100%
 
Consultant Selection
02/01/08
02/07/08
100%
 
Scope of Services
02/08/08
02/12/08
100%
 
Approve/Reject
02/13/08
02/13/08
100%
 
Notice to Proceed
02/14/08
02/14/08
100%
 
Data Gathering
07/29/08
08/13/08
100%
 
SWFWMD Meeting
07/29/08
07/29/08
100%
 
Meeting with Manasota Key
08/13/08
08/13/08
100%
 
Design and Permitting
03/17/08
06/17/09
100%
 
30% Plan Review
03/17/08
07/18/08
100%
 
60% Plan Review
07/21/08
02/27/09
100%
 
100% Plan Review
03/02/09
06/17/09
100%
 
SWFWMD Permit 11/24/08 05/01/09 100%  
Construction
10/22/09
03/26/10
0%  
Construction
10/22/09 03/20/10
0%
 
Substantial Completion/Rating
03/21/10 03/21/10
0%
 
Punchlist Items
03/22/10 03/22/10
0%
 
As-Builts Received
03/23/10 03/23/10
0%
 
Submit As-Builts
03/24/10 03/24/10
0%
 
Final Invoice
03/25/10 03/25/10
0%
 
Close Project
03/26/10 03/26/10
0%