Project Status Update
Manasota Key Phase 1 and 2 Construction
CIP Project N064108
CIP Project N064109
This project provides for the construction of drainage improvements along Gulf Boulevard, from Beach Drive to Holiday Drive, in South Manasota Key. This construction project involves the combination of the Phase 1 and Phase 2 designs.
Future dates and durations associated with this project are approximations and are dependent on funding, permitting, weather, and contractor availability. Permitting for some projects, depending on their complexity, can take years to obtain.
| Project Task |
Start Date |
Finish Date |
% Complete |
Contractor |
|---|---|---|---|---|
| Request for Proposal | 01/07/08 |
02/14/08 |
100% |
|
Request to Purchasing |
01/07/08 |
01/14/08 |
100% |
|
Proposal Received |
01/18/08 |
01/31/08 |
100% |
|
Consultant Selection |
02/01/08 |
02/07/08 |
100% |
|
Scope of Services |
02/08/08 |
02/12/08 |
100% |
|
Approve/Reject |
02/13/08 |
02/13/08 |
100% |
|
Notice to Proceed |
02/14/08 |
02/14/08 |
100% |
|
| Data Gathering | 07/29/08 |
08/13/08 |
100% |
|
SWFWMD Meeting |
07/29/08 |
07/29/08 |
100% |
|
Meeting with Manasota Key |
08/13/08 |
08/13/08 |
100% |
|
Design and Permitting |
03/17/08 |
06/17/09 |
100% |
|
30% Plan Review |
03/17/08 |
07/18/08 |
100% |
|
60% Plan Review |
07/21/08 |
02/27/09 |
100% |
|
| 100% Plan Review | 03/02/09 |
06/17/09 |
100% |
|
| SWFWMD Permit | 11/24/08 | 05/01/09 | 100% | |
| Construction | 10/22/09 |
03/26/10 |
0% | |
Construction |
10/22/09 | 03/20/10 | 0% |
|
Substantial Completion/Rating |
03/21/10 | 03/21/10 | 0% |
|
Punchlist Items |
03/22/10 | 03/22/10 | 0% |
|
As-Builts Received |
03/23/10 | 03/23/10 | 0% |
|
Submit As-Builts |
03/24/10 | 03/24/10 | 0% |
|
Final Invoice |
03/25/10 | 03/25/10 | 0% |
|
Close Project |
03/26/10 | 03/26/10 | 0% |