This project provides for the widening of Kings Highway, from Sandhill Boulevard to the DeSoto County line. This section will be a four-lane, divided roadway.

Future dates and durations associated with this project are approximations and are dependent on funding, permitting, weather, and contractor availability. Permitting for some projects, depending on their complexity, can take years to obtain.

Project Task
Start
Finish
Complete
Contractor
Design
11/15/06
2/29/08
100%
 
Permitting
11/12/07
3/28/08
100%
 
Right-of-Way
11/5/07
10/1/08
100%
 
Construction On Hold      

Comments:

Construction is on hold due to Board action.