Public Works

Project Status Update

Harbour Heights Waterway Maintenance Dredging

CIP Project C390705

Chuck Mopps, Project Manager

This project is designed to facilitate safe navigation within the Harbour Heights waterway system by removing 16,841 cubic yards of silted material and placing it on upland sites.

Future dates and durations associated with this project are approximations and are dependent on funding, permitting, weather, and contractor availability. Permitting for some projects, depending on their complexity, can take years to obtain.

Project Task
Start Date
Finish Date
% Complete
Contractor
Mobilize Equipment 07/27/09 07/27/09 70% Marine Contracting Group
Set Up Spoil Sites 07/27/09 08/14/09 20%  
Group 1 Canals 08/17/09 01/19/10 0%  
San Marino Canal 08/17/09 09/04/09 0%  
San Salvador Canal 09/07/09 10/14/09 0%  
San Salvador Entrance 10/15/09 10/21/09 0%  
Santa Barbara Canal 10/22/09 11/13/09 0%  
Dover Canal 11/16/09 12/16/09 0%  
Dover Canal Entrance 12/17/09 12/21/09 0%  
Santa Clara Canal 12/22/09 01/19/10 0%  
Group 2 Canals 08/24/09 01/08/10 2%  
Desoto Canal 08/24/09 10/16/09 15%  
Balboa Canal 10/19/09 12/02/09 0%  
Balboa Extension 12/03/09 12/09/09 0%  
Versailles Extension 12/10/09 12/16/09 0%  
Vincennes Canal 12/17/09 12/25/09 0%  
Vendrome Canal 12/28/09 01/04/10 0%  
Viceroy Canal 01/05/10 01/08/10 0%