Public Works

Project Status Update

Gulf Cove Waterway Dredging

CIP Project C390704

Chuck Mopps, Project Manager

This project is designed to facilitate safe navigation within the Gulf Cove waterway system by removing approximately 26,000 cubic yards of silted material and placing it on upland sites.

Future dates and durations associated with this project are approximations and are dependent on funding, permitting, weather, and contractor availability. Permitting for some projects, depending on their complexity, can take years to obtain.

Project Task
Start Date
Finish Date
% Complete
Contractor
Spoil Site Prep 12/15/08 12/23/08 100%  
Environmental Controls 12/29/08 09/20/09 95%  
Mobilize Land-Based Equipment 01/05/09 07/16/09 100%  
Survey Initial Channels to be Dredged 01/07/09 01/08/09 100% Coastal Engineering
Clear Site 06/22/09 10/15/09 19%  
Northern Canals and Separate Spoil Site 12/11/08 09/22/09 99%  
Mid Canals 01/21/09 09/18/09 100%  
Southern Canals 06/02/09 09/21/09 100%