Public Works

Project Status Update

Greater Port Charlotte Water Control Structures Design

CIP Project C390304

John DeGiovine, Project Manager

The design of this structure is consistent with Master Stormwater Management Plan requirements. Replacement of this structure is part of the overall plan to improve the drainage flow through the canal system, up to the 100-year storm event.

Future dates and durations associated with this project are approximations and are dependent on funding, permitting, weather, and contractor availability. Permitting for some projects, depending on their complexity, can take years to obtain.

Project Task
Start Date
Finish Date
% Complete
Contractor
Project Kick-Off
03/31/09
06/30/09
100%
 
Notice to Proceed
03/31/09
03/31/09
100%
 
Establish Stakeholders Team
04/21/09
04/30/09
100%
 
Stakeholders/Scoping Meeting
05/05/09
05/05/09
100%
 
Survey
05/06/09
05/26/09
100%
 
Geotechnical Investigation
05/08/09
06/30/09
100%
 
Construction Plans (Engineering Phase)
05/28/09
02/12/10
58%
 
30% "Concept" Design
05/28/09
06/09/09
100%
 
30% Review
06/10/09
06/23/09
100%
 
60% "Submittal" Design
06/24/09
07/24/09
100%
 
60% Review
07/27/09
08/11/09
100%
 
90% Construction Design
08/12/09
11/19/09
52%
 
90% Review
11/20/09
12/03/09
0%
 
100% Construction Drawings
01/08/10
02/04/10
0%
 
100% CD and Estimate
02/12/10
02/12/10
0%
 
SWFWMD ERP
05/12/09
02/11/10
7%  
Pre-Application Meeting
05/12/09
05/12/09 100%  
Initial Application Submittal
09/25/09
09/25/09
100%
 
Initial Review
09/28/09 10/28/09 20%  
RAI
10/29/09 10/29/09
0%
 
RAI Response
10/30/09 11/19/09
0%
 
RAI Submittal
11/20/09 11/20/09
0%
 
RAI Review
11/23/09 12/23/09
0%
 
CLAR
12/24/09 12/24/09
0%
 
CLAR Response
12/25/09 01/07/10
0%
 
CLAR Submittal
01/08/10 01/08/10
0%
 
CLAR Review
01/11/10 02/10/10
0%
 
SWFWMD Approval
02/11/10 02/11/10
0%
 
Charlotte County Utilities
08/12/09 12/29/09
24%
 
Initial Application Submittal
08/12/09 08/12/09
100%
 
Initial Review
08/24/09 09/22/09
50%
 
Incorporate Comments 09/23/09 09/29/09 0%  
FDEP Application 11/27/09 11/27/09 0%  
FDEP Application Review 11/30/09 12/25/09 0%  
FDEP Approval 12/29/09 12/29/09 0%