Public Works
Project Status Update
Greater Port Charlotte Water Control Structures Design
John DeGiovine, Project Manager
The design of this structure is consistent with Master Stormwater Management Plan requirements. Replacement of this structure is part of the overall plan to improve the drainage flow through the canal system, up to the 100-year storm event.
Future dates and durations associated with this project are approximations and are dependent on funding, permitting, weather, and contractor availability. Permitting for some projects, depending on their complexity, can take years to obtain.
| Project Task |
Start Date |
Finish Date |
% Complete |
Contractor |
|---|---|---|---|---|
| Project Kick-Off | 03/31/09 |
06/30/09 |
100% |
|
Notice to Proceed |
03/31/09 |
03/31/09 |
100% |
|
Establish Stakeholders Team |
04/21/09 |
04/30/09 |
100% |
|
Stakeholders/Scoping Meeting |
05/05/09 |
05/05/09 |
100% |
|
Survey |
05/06/09 |
05/26/09 |
100% |
|
Geotechnical Investigation |
05/08/09 |
06/30/09 |
100% |
|
Construction Plans (Engineering Phase) |
05/28/09 |
02/12/10 |
58% |
|
30% "Concept" Design |
05/28/09 |
06/09/09 |
100% |
|
| 30% Review | 06/10/09 |
06/23/09 |
100% |
|
60% "Submittal" Design |
06/24/09 |
07/24/09 |
100% |
|
60% Review |
07/27/09 |
08/11/09 |
100% |
|
90% Construction Design |
08/12/09 |
11/19/09 |
52% |
|
90% Review |
11/20/09 |
12/03/09 |
0% |
|
100% Construction Drawings |
01/08/10 |
02/04/10 |
0% |
|
| 100% CD and Estimate | 02/12/10 |
02/12/10 |
0% |
|
| SWFWMD ERP | 05/12/09 |
02/11/10 |
7% | |
Pre-Application Meeting |
05/12/09 |
05/12/09 | 100% | |
Initial Application Submittal |
09/25/09 |
09/25/09 |
100% |
|
Initial Review |
09/28/09 | 10/28/09 | 20% | |
RAI |
10/29/09 | 10/29/09 | 0% |
|
RAI Response |
10/30/09 | 11/19/09 | 0% |
|
RAI Submittal |
11/20/09 | 11/20/09 | 0% |
|
RAI Review |
11/23/09 | 12/23/09 | 0% |
|
CLAR |
12/24/09 | 12/24/09 | 0% |
|
CLAR Response |
12/25/09 | 01/07/10 | 0% |
|
CLAR Submittal |
01/08/10 | 01/08/10 | 0% |
|
CLAR Review |
01/11/10 | 02/10/10 | 0% |
|
SWFWMD Approval |
02/11/10 | 02/11/10 | 0% |
|
Charlotte County Utilities |
08/12/09 | 12/29/09 | 24% |
|
Initial Application Submittal |
08/12/09 | 08/12/09 | 100% |
|
Initial Review |
08/24/09 | 09/22/09 | 50% |
|
| Incorporate Comments | 09/23/09 | 09/29/09 | 0% | |
| FDEP Application | 11/27/09 | 11/27/09 | 0% | |
| FDEP Application Review | 11/30/09 | 12/25/09 | 0% | |
| FDEP Approval | 12/29/09 | 12/29/09 | 0% |