Public Works

Project Status Update

Edgewater/Flamingo Corridor Phase 1

CIP Project C419001 (83008)

Brian Barnes, Project Engineer

The initial phase of the Edgewater/Flamingo corridor project consists of the purchase of right-of-way, preliminary engineering design, permitting, and mitigation of a new two-lane roadway from SR 776 to Collingswood Boulevard. The project excludes the road that lies within Murdock Village. It is anticipated that stormwater elements of this phase and later phases will be included as funding permits. It is anticipated that impact fees from the Murdock Village Development will fund the majority of the project construction. FDOT has recently agreed to participate in the design and implementation of a traffic signal at SR 776 and Flamingo. The cost of Tippecanoe II mitigation land acquisition is also included.

Future dates and durations associated with this project are approximations and are dependent on funding, permitting, weather, and contractor availability. Permitting for some projects, depending on their complexity, can take years to obtain.

Project Task
Start Date
Finish Date
% Complete
Contractor
Design
06/01/06
05/01/10
93%
Wilbur Smith
30% Review
06/01/06
02/26/08
100%
 
60% Review
01/08/08
12/01/08
100%
 
90% Review
12/02/08
02/01/10
95%
 
100% Review
02/11/10
05/01/10
0%