Public Works

Project Status Update

Coral Creek Bridge Replacement

CIP Project C419801

Chuck Koons, Project Engineer

This project will replace the existing bridge on CR 771 over Coral Creek in Placida. The new structure will enhance recreational access by increasing the span between the bridge supports and adding about one foot of additional clearance for boaters. The project will also eliminate the sharp curve at the junction of CR 775 and CR 771.

Future dates and durations associated with this project are approximations and are dependent on funding, permitting, weather, and contractor availability. Permitting for some projects, depending on their complexity, can take years to obtain.

Project Task
Start Date
Finish Date
% Complete
Contractor
Design
04/01/02
03/25/09
100%
Keith and Schnars
Initial Design
04/01/02
12/26/05
100%
 
Utility Relocation Design
06/16/06
11/30/07
100%
 
Permit Modifications
12/03/07
08/27/08
100%
 
100% Plan Review
08/28/08
09/10/08
100%
 
Design Corrections
09/11/08
03/25/09
100%  
Plans Complete
03/25/09 03/25/09
100%
 
Permitting
03/03/03
11/07/08
100%
 
Southwest Florida Water Management District
03/03/03
09/15/05
100%
 
Florida Department of Environmental Protection
03/03/03
12/26/05
100%
 
US Fish & Wildlife Service
03/03/03
09/15/05
100%
 
Florida Fish & Wildlife Conservation
03/03/03
09/15/05
100%
 
Purchase of Mitigation Credits
03/01/06
08/29/06
100%
 
Archeological Survey
03/01/06
05/09/07
100%
 
Submerged Lands Easement
03/01/06
09/26/06
100%
 
SHPO Review
05/10/07
10/24/07
100%
 
Addended Report to SHPO
11/27/07
11/07/08
100%
 
US Coast Guard
08/15/03
01/02/08
100%
 
USACOE
07/11/07
12/21/07
100%
 
Construction
02/04/08
10/15/10
65%
 
Checklist Process
02/04/08
03/12/08
100%
 
Documents to Purchasing
03/12/08
04/18/08
100%
 
Pre-Bid Meeting
04/18/08
04/18/08
100%
 
Bid Opening
04/18/08
06/25/08
100%
 
Goldenrod Preparation
06/25/08
07/09/08
100%
 
BCC Approval
07/22/08
07/22/08
100%
 
Pre-Construction Meeting
07/22/08
08/06/08
100%
 
Procurement
08/06/08
09/29/08
100%
 
Ground Breaking
09/29/08
09/29/08
100%
 
Notice to Proceed
09/29/08
09/29/08
100%
 
Construction
09/29/08
10/15/10
55%
 
Project Close-Out 10/15/10 07/15/11 0%  
Substantial Completion
10/15/10
12/17/10
0%
 
Punchlist Items
12/17/10
01/28/11
0%
 
As-Builts Received
01/28/11
04/22/11
0%
 
Submit As-Builts
04/22/11
06/03/11
0%
 
Final Invoice
06/03/11
07/15/11
0%
 
Close Project
07/15/11
07/15/11
0%