Public Works

Project Status Update

South Gulf Cove Entry Features

CIP Project C410905

John Elias, Project Manager

This project consists of all design aspects for the entry features, which include, but are not limited to, four entrance signs and ancillaries, landscaping and irrigation, points of service for electric and water, and decorative lighting. The locations for the signs are at four intersections of County Road 771--Keystone Boulevard, Ingraham Boulevard, San Domingo Boulevard, and Appleton Boulevard.

Future dates and durations associated with this project are approximations and are dependent on funding, permitting, weather, and contractor availability. Permitting for some projects, depending on their complexity, can take years to obtain.

Project Task
Start Date
Finish Date
% Complete
Contractor
Request for Design Proposal
02/01/09
03/12/09
100%
 
Request to Purchasing
02/01/09
02/02/09
100%
 
Proposal Received
02/03/09
02/03/09
100%
 
Consultant Selection
02/04/09
02/12/09
100%
 
Receive Scope of Services
02/13/09
02/19/09
100%
 
Notice to Proceed
02/20/09
02/26/09
100%
 
Signed Contract
03/12/09
03/12/09
100%
 
Design
04/21/09
07/23/09
100%
Kimley Horn
30% Plan Review
04/21/09
05/18/09
100%
 
60% Plan Review
05/19/09
06/29/09
100%
 
90% Plan Review
06/30/09
07/13/09
100%
 
100% Plan Review
07/17/09
07/23/09
100%
 
Construction
08/05/09
01/05/10
35%  
Checklist Process
08/05/09
08/05/09 100%  
Documents to Purchasing
08/06/09 08/24/09
100%
 
Pre-Bid Date Scheduled
09/24/09 10/13/09 100%  
Bid Opening
10/14/09 10/14/09
100%
 
Goldenrod Preparation
10/22/09
10/22/09
0%
 
BCC Approval
10/23/09 10/23/09
0%
 
Pre-Construction Meeting
10/26/09 10/26/09
0%
 
Notice to Proceed
10/27/09 10/27/09
0%
 
Construction
10/28/09 12/29/09
0%
 
Substantial Completion/Rating
12/30/09 12/30/09
0%
 
Punchlist Items
12/31/09 12/31/09
0%
 
As-Builts Received
01/01/10 01/01/10
0%
 
Submit As-Builts
01/04/10 01/04/10
0%
 
Final Invoice
01/05/10 01/05/10
0%