Chancellor Drainage Control Structure at Jupiter Waterway

John Elias, Project Manager

This project provided for the construction of a redesign of the Jupiter Waterway drainage system.

Future dates and durations associated with this project are approximations and are dependent on funding, permitting, weather, and contractor availability. Permitting for some projects, depending on their complexity, can take years to obtain.

Project Task
Start Date
Finish Date
% Complete
Contractor
Construction 11/10/08 10/06/09 100% Armadillo Underground
Checklist Process
11/10/08 11/20/08 100%  
Documents to Purchasing
12/01/08 12/01/08 100%  
Pre-Bid Date Scheduled
02/05/09 02/05/09 100%  
Bid Opening
02/18/09 02/18/09 100%  
Goldenrod Preparation
02/23/09 02/27/09 100%  
BCC Approval
03/24/09 03/24/09 100%  
Pre-Construction Meeting
04/01/09 04/01/09 100%  
Notice to Proceed
04/27/09 04/27/09 100%  
Construction
04/28/09
08/14/09
100%  
Substantial Completion
08/14/09 08/14/09 100%  
Punchlist Items
08/17/09 09/03/09 100%  
As-Builts Received
09/04/09 09/04/09 100%  
Final Invoice from Contractor 09/17/09 10/05/09 100%