Project Status Update

Chancellor Drainage Control Structure at Cheshire Waterway

John Elias, Project Manager

This project provided for the construction of a redesign of the Cheshire Waterway drainage system.

Future dates and durations associated with this project are approximations and are dependent on funding, permitting, weather, and contractor availability. Permitting for some projects, depending on their complexity, can take years to obtain.

Project Task
Start Date
Finish Date
% Complete
Contractor
Construction
11/10/08
10/21/09
100%
Southwest Utilities
Checklist Process
11/10/08
11/10/08
100%
 
Documents to Purchasing
12/01/08 12/01/08 100%  
Pre-Bid Date Scheduled
04/09/09 04/09/09 100%  
Bid Opening
04/22/09 04/22/09 100%  
Goldenrod Preparation
04/29/09 05/05/09 100%  
BCC Approval
05/12/09 05/12/09 100%  
Pre-Construction Meeting
05/14/09 05/14/09 100%  
Notice to Proceed
05/29/09 05/29/09 100%  
Construction
05/26/09
07/29/09
100%
 
Substantial Completion
07/29/09 07/29/09 100%  
Punchlist Items
07/31/09
07/31/09
100%  
As-Builts Received
08/24/09 08/24/09 100%  
Final Invoice
10/20/09
10/20/09
100%