Chancellor Drainage Control Structure at Apollo Waterway

John Elias, Project Manager

This project provided for the construction of a redesign of the Apollo Waterway drainage system.

Future dates and durations associated with this project are approximations and are dependent on funding, permitting, weather, and contractor availability. Permitting for some projects, depending on their complexity, can take years to obtain.

Project Task
Start Date
Finish Date
% Complete
Contractor
Construction 11/10/08 09/23/09 100% Dave Foote Environmental
Checklist Process
11/10/08 11/10/08 100%  
Documents to Purchasing
12/01/08 12/01/08 100%  
Pre-Bid Date Scheduled
02/18/09 02/18/09 100%  
Bid Opening
03/11/09 03/11/09 100%  
Goldenrod Preparation
04/21/09 05/10/09 100%  
BCC Approval
04/28/09 04/28/09 100%  
Pre-Construction Meeting
05/06/09 05/16/09 100%  
Notice to Proceed
05/26/09 05/26/09 100%  
Construction
05/26/09
09/06/09
100%  
Substantial Completion
09/07/09 09/07/09 100%  
Punchlist Items
09/08/09 09/15/09 100%  
As-Builts Received
09/16/09 09/20/09 100%