Chancellor Drainage Control Structure at Apollo Waterway
This project provided for the construction of a redesign of the Apollo Waterway drainage system.
Future dates and durations associated with this project are approximations and are dependent on funding, permitting, weather, and contractor availability. Permitting for some projects, depending on their complexity, can take years to obtain.
| Project Task |
Start Date |
Finish Date |
% Complete |
Contractor |
|---|---|---|---|---|
| Construction | 11/10/08 | 09/23/09 | 100% | Dave Foote Environmental |
Checklist Process |
11/10/08 | 11/10/08 | 100% | |
Documents to Purchasing |
12/01/08 | 12/01/08 | 100% | |
Pre-Bid Date Scheduled |
02/18/09 | 02/18/09 | 100% | |
Bid Opening |
03/11/09 | 03/11/09 | 100% | |
Goldenrod Preparation |
04/21/09 | 05/10/09 | 100% | |
BCC Approval |
04/28/09 | 04/28/09 | 100% | |
Pre-Construction Meeting |
05/06/09 | 05/16/09 | 100% | |
Notice to Proceed |
05/26/09 | 05/26/09 | 100% | |
Construction |
05/26/09 | 09/06/09 |
100% | |
Substantial Completion |
09/07/09 | 09/07/09 | 100% | |
Punchlist Items |
09/08/09 | 09/15/09 | 100% | |
As-Builts Received |
09/16/09 | 09/20/09 | 100% |