Building Construction Services - Land Development

Stormwater Plan Approval Requirements

Download Stormwater Plan Review Application

All of our codes can be viewed at Municode

Click Here For StormWater Ordinance

 

(Ordinance 89-37) (Code Sec. 3-5-111)
 

A. Required for all site development; except (Code Sec. 3-5-113)

(1) Single, Duplex & Triplex Residential Units
(2) Sheds and other accessory uses allowed in (1) above
(3) Fences
(4) Any proposal for a development activity causing insignificant impacts upon stormwater facilities (to be determined by the Land Development Department)
 

B. Submittal Procedures/Requirements

(1) Two signed and sealed sets of plans.
(2) One signed and sealed set of drainage calculations.
(3) One completed application.
(4) SWFWMD or SFWMD approval letter.
(5) Fee:

  1. 10 acres or less - $580.00
  2. Each additional acre - $21.00 per acre or part thereof.
  3. Resubmission after 2 rejections - $270.
  4. Plan modification after 1st approval $270.
  5. Stormwater re-inspection fee for each re-inspection - $160.

 

C. Contact

(1) Stormwater Plans Examiner 941.623.1012
 

D. General Information

(1) Response Review time from 5 to 30 days depending on complexity.
(2) State Water Management District approval or exemption required.
(3) Design of control structure based on a 25-year 24-hour storm event.
(4) NPDES required.